Saronbrug - Surinam
Delivery of a 225 meter long double lane truss bridge in 3 spans of each 75 meter, incl 2 side external pedestrian walk ways.
The bridge was designed and produced in The Netherlands and shipped to Surinam. A local contractors installed the bridge and the concrete deck.
Szczegóły projektu
Rozwiązanie
Truss bridge
Typ
JTB
Client
Ministry of Public Works of Surinam
Number of Bridges
1
Bridge Length
225 meter
Bridge width
8 meter
Completed
2014
-
The Saron bridge was opened on 28 September 2014.
-
The bridge is 225 mets long and 16 meters wide in total.
-
The bridge was part of a project that included 1 km of new road and a roundabout.
-
The bridge has reduced the heavily trafficed Coesewijne bridge.